| SSPR - Site Selection Process Review | |
| List of activities within the module | |
| Purpose | Provides the MSs with an independent review of the adherence to the IAEA guidance on the subject and the appropriateness of the selection of exclusion and screening criteria, and their use in the ranking of the sites. |
| Audience | Regulator, Operator |
| Team composition | 2-3 staff members and select subject matter experts(if required) |
| Duration | 1 pre-mission prep, 1 week in field , I week post mission reporting |
| Expected output | Report on SSPR |
| Average usage in 2005-2010 | |
| Recommended frequency | As and when request received from MS |
| Resource requirements | House staff & experts |
| Prerequisites | None |
| Point of Contact in IAEA | Head, ISSC, NSNI |
| Public outreach | Through www.issc.iaea.org |
| Required follow-up | As required till activity completed |
| ISER - Integrated Site Evaluation Review | |
| List of activities within the module | |
| Purpose | A multidisciplinary review which address all the requirements that a site has to meet for the construction of a nuclear installation. Provides the MSs with an independent review of the adherence to the IAEA safety requirements and the level of detail in site investigation to establish the site’s capacities to support the installation’s design needs. |
| Audience | Regulator |
| Team composition | 2-3 staff members and subject matter experts covering the full range of site characterization |
| Duration | 1 pre-mission prep, 1 week in field , 3 week post mission reporting |
| Expected output | Report on ISER |
| Average usage in 2005-2010 | |
| Recommended frequency | As and when request received from MS |
| Resource requirements | House staff & experts |
| Prerequisites | None |
| Point of Contact in IAEA | Head ISSC, NSNI |
| Public outreach | Through www.issc.iaea.org |
| Required follow-up | As required till activity completed |
| SHER - Site Hazard evaluation Review | |
| List of activities within the module | |
| Purpose | Provides the MSs with an independent review of the adherence to the IAEA safety requirements and the level of detail in site investigation to establish the appropriate estimate of a specific hazard at the site during the lifetime of the installation |
| Audience | Regulator, Operator |
| Team Composition | 2-3 staff members and select subject matter experts for spe cific hazards that need to be characterized |
| Duration | 1 pre-mission prep, 1 week in field , 3 week post mission reporting |
| Expected output | Report on SHER |
| Average usage in 2005-2010 | |
| Recommended frequency | As and when request received from MS |
| Resource requirements | House staff & experts |
| Prerequisites | None |
| Point of Contact in IAEA | Head, ISSC, NSNI |
| Public outreach | Through www.issc.iaea.org |
| Required follow-up | As required till activity completed |
| SR-SSC - Safety Review of SSC against External and Internal Hazards | |
| List of activities within the module | |
| Purpose | Provides the MSs with an independent review of the adherence to the IAEA safety requirements in the design of SSC’s to meet the demands of the site specific hazard. |
| Audience | Regulator |
| Team Composition | 2-3 staff members and select subject matter experts |
| Duration | 1 pre-mission prep, 1 week in field , 3 week post mission reporting |
| Expected output | Report on SR-SSC |
| Average usage in 2005-2010 | |
| Recommended frequency | As and when request received from MS |
| Resource requirements | House staff & experts |
| Prerequisites | None |
| Point of Contact in IAEA | Head ISSC, NSNI |
| Public outreach | Through www.issc.iaea.org |
| Required follow-up | As required till activity completed |
| SEAR - Site Environmental Assessment Review | |
| List of activities within the module | |
| Purpose | Provides the MSs with an independent review of the adherence to the IAEA environmental assessment requirement. |
| Audience | Regulator, Operator |
| Team Composition | 2-3 staff members and select subject matter experts as required |
| Duration | 1 pre-mission prep, 1 week in field , 3 week post mission reporting |
| Expected output | Report on SAER |
| Average usage in 2005-2010 | |
| Recommended frequency | As and when request received from MS |
| Resource requirements | House staff & experts |
| Prerequisites | Site need to be established. |
| Point of Contact in IAEA | Head ISSC, NSNI |
| Public outreach | Through www.issc.iaea.org |
| Required follow-up | As required till activity completed |