COMMISSIONING
List of activities within the module The commissioning  covers all the activities to be performed on Systems, structures and components to bring them to an operating mode. This include pre-operational tests, fuel loading and subcritical tests, initial criticality and low power tests and power tests. The pre-operating OSART will cover the commissioning organisation, functions and responsibilities in commissioning activitiesinterfaces between the participants in the commissioning program, assesment, qualification and training, maintenance, plant handover, quality assurance, emergency arragements, feedback  experience from commissioning.
Purpose The purpose of the Pre-operational OSART is to make recommendations which will enable a safe and high quality commissioning program as well as to make sure that the plant has been constructed in accordance with the design and can be operated safely. 
Audience Operators
Team composition Operational safety assessment expert team
Duration three weeks
Expected output Recommendations on the preparedness of the operating organisation to fulfil its responsibility for nuclear safety 
Average usage in 2005-2010 One or two per year 
Recommended frequency Upon request
Resource requirements Funding is made either by the requesting party or TC for 3 IAEA safety officers + 10 international experts from utilities, regulator, technical support organizations 
Prerequisites Agreement between requesting party and IAEA; advance information package available before the review.
Point of Contact in IAEA Gabor Vamos ( G.Vamos@iaea.org )
Public outreach N/A
Required follow-up YES
In Depth Safety Culture ( Under Development )
List of activities within the module The integrated In-depth Safety Culture-Operational Safety Assessment Review Team covers all activities of an operating organisation . 
Purpose Perform a joint assesment of operational safety and safety culture and provide recommendations  in these respect.                                                                                                    Shall replace SCART
Audience Operators
Team composition Operational safety assessment expert team
Duration three weeks
Expected output Reports on the preparedness of the operating organisation to fulfil its responsibility for nuclear safety 
Average usage in 2011 2 missions ( Brazil and South Africa )
Recommended frequency Upon request
Resource requirements Funding is made either by the requesting party or TC for 3 IAEA safety officers + 10 international experts from utilities, regulator, technical support organizations +2 to 3 safety culture experts
Prerequisites Agreement between requesting party and IAEA; preparatory meeting and seminar for OSART and safety culture assessment methodology ( presentation of tools used as regard to the safety culture assesment: survey, interviews, field observations, focused groups, documents review) 
Point of Contact in IAEA Pierre Gest ( P.Gest@iaea.org )
Public outreach N/A
Required follow-up YES
PROBABILISTIC SAFETY ASSESSMENT
List of activities within the module  Probabilistic safety assessment :
- PSA development
- PSA updating programme
- PSA applications programme
- PSA applications in connection with plant operation
- PSA applications in connection with risk informed technical specifications
- PSA applications in connection with plant modification and licensing
- Interactions with Regulatory Body
purpose Check the objectives and scope of the PSA. Check that the PSA scope supports the stated objectives. Compare the objectives and scope of the PSA with those that are required by national regulations. Compare the scope with the scope of PSA that is required for the intended PSA applications. The scope of PSA for different applications should be at least such as it is described in the IAEA Safety Guides  on Level-1 and Level-2 PSA (Refs. [4, 5]; additionally the TECDOC-1511 can be consulted on the issue 
Audience Operators/licensees
Team composition Standard OSART team + 1 additional expert of the field
Duration 3weeks
Expected output recommendations on 
Average usage from 2005 to 2011  ?
Recommended frequency To be defined
Resource requirements Funding is made either by the requesting party or TC for 3 IAEA safety officers + 10 international experts from utilities, regulator, technical support organizations + 1 additional expert 
Prerequisites Request from member state, preparatory meeting.
Point of Contact in IAEA Irina Kouzmina (I.Kouzmina@iaea.org)
Public outreach N/A
Required follow-up YES
Severe Accident Management 
List of activities within the module 1) Definition of overall AMP and its compliance with the national requirements, 2) Quality and extent of the accident analysis to support the AMP, 3) Assessment of plant vulnerabilities, 4) Development of severe accident management strategies, 5) Evaluation of plant equipment and instrumentation.6) Development of accident management procedures and guidelines, 7) Verification and validation of the procedures and guidelines, 8) Integration between AMP and plant emergency arrangements, 9) Staffing and qualification, 10) Training needs and performance, 11) AMP revisions.
Purpose the objective is to assist at the utility and NPP (i.e. licensee) level in effective plant specific AMP preparation, development and implementation. However, assistance can also be provided to the regulatory body in its reviewing of AMPs. Objectives of the safety service can be summarized as follows:
• To explain to licensee personnel principles and possible approaches in effective implementation of AMP based on experience world-wide;
• To give opportunities to experts from the host plant to broaden their experience and knowledge in the field;
• To perform an objective assessment of the status in various phases of AMP implementation, compared with international experience and practices;
• To provide the licensee with suggestions and assistance for improvements in various stages of AMP implementation.
Audience Operators/Licensees
Team composition 1 Team leader from IAEA + up to 5 experts
Duration 3 weeks
Expected output recommendations and advice
Average usage from 2005 - 2011 ?
Recommended frequency To be defined
Resource requirements Funding is made either by the requesting party or TC for 3 IAEA safety officers + 10 international experts from utilities, regulator, technical support organizations + 1 additional experts
Prerequisites Request from Member States and advance information package.
Point of Contact in IAEA Manwoong KIM (M.Kim@iaea.org) 
Public outreach N/A
Required follow-up YES